|
|
Case
Studies > Greater Bargoed Community Regeneration
The scheme objective
was to provide improved transportation links between the communities
of Bargoed, Aberbargoed and Gilfach and to reduce traffic volumes
on the A469 and congestion to the centres of these settlements.
The scheme is located in the Rhymney Valley and follows the valley
floor between Bargoed and Gilfach to the west and Aberbargoed
to the east. The site is a former colliery. The colliery buildings
were demolished in the mid 1990’s, in conjunction with a land
reclamation scheme which reshaped the former colliery waste tips.
These have now been further shaped to accommodate the footprint
of the proposed highway, with plateaus constructed for future
retail and industrial development.

The scheme involved
the construction of approximately 3.5km of single carriageway
highway and associated structures. This involved the construction
of four new interchanges to tie into the existing road network,
three bridges to span the River Rhymney and Rhymney Valley Railway,
a new rail tunnel at the northern end of the site and several
retaining structures to enable the construction of further plateaus
for retail and industrial development. The scheme interfaces with
residential areas at five locations, including a school.
Gregory Environmental
became involved with the project with the principal contractor
‘Hochtief Griffiths
JV’ during the successful tender stage, we then took the project
through the discharge of planning conditions, the consenting process
and then onto site. We developed the Environmental Management
System and then applied this throughout the course of the project.
Works carried out were:
- Environmental aspect identification
- EMS development
- Consenting
- Section 61, Flood Defence, Waste Management, Discharge and Abstraction
Consents.
- Design and implementation of a scheme for the in-situ encapsulation
of Japanese Knotweed, including the consenting process with the
EA
- Ecological supervision
- Liaison with statutory bodies and third parties including presentations
on the scheme to interested parties.
- Training including toolbox talks and formal training sessions
- Noise, Vibration,
Dust and Water
Quality Monitoring.
- Design and construction of water quality treatment systems
- Site inspection
- Internal auditing
back to case studies >
|
|